Maintenance on the diverting canal of the power station of Saint Clair in the towns of Chambave and Pontey between 0.000 – 3500 and 7000 – 10500.
MAIN WORKS:
• Works in reinforced concrete
• Demolitions
• Strengthening works with micropile and cement grouting
• Metal structural work – flood gates
| State |
Completato |
| Start Date |
19/03/2012 |
| End Date |
02/05/2012 |
| Client |
C.V.A. S.p.A. |
| Planning Company |
C.V.A. S.p.A. |
| Country |
ITALY, IT |
| Contract |
Maintenance on the diverting canal of the power station of Saint Clair in the towns of Chambave and Pontey between 0.000 – 3500 and 7000 – 10500. |
| Work Type |
SOA “OG1” |